days after, the time due for payment, interest of between 0.5% and 10%
per day shall be applied to the contract sum.
That while the first sum of Thirty – five million seven hundred and
sixteen thousand, four hundred and twenty two naira (N35, 716,422.00)
only has been paid to the Plaintiff, the balance of twenty million, six
hundred and ninety eight thousand, nine hundred and twenty naira
(N20, 698, 920.00) only has remained unpaid till date despite several
demands from the Defendants.
Accordingly, the Plaintiff seeks the following reliefs from this Court:
1. AN ORDER, compelling the Defendants to pay the Plaintiff the sum
of Twenty million, six hundred and ninety eight thousand, nine
hundred and twenty naira (N20, 698,920.00) being the balance of
the contract sum of goods and services rendered to the Defendant
since 15th December, 2014.
2. 10% Interest per day on the sum of twenty million, six hundred and
ninety eight thousand, nine hundred and twenty naira (N20,
698,920.00) only from the 16th of April 2015 till the sum is finally paid
to the Applicant.
3. General damages in the sum of five hundred million naira (N500,
000,000.00) against the Defendants.
3